Connecticut Route 11

As a result, many people in New London County, who would have benefitted most from the original project, derisively refer to the highway as "Route 5½" for its half-done construction.

The EIS was published three months behind schedule due to a dispute between ConnDOT and the consulting firm that prepared the EIS—the Macguire Group—over payment for services rendered.

In December 2007, Federal Highway Administration extended the FEIS review period through the end of January 2008 to provide the EPA with a detailed environmental mitigation plan.

Additionally state and federal elected officials requested the FHWA and ConnDOT present a detailed financial management plan for activities related to the extension.

In 2011, Governor Dan Malloy indicated that completing Route 11 to the I-95/I-395 interchange was a high priority for the state and ordered ConnDOT to resume environmental and funding studies.

While it would have been built as a fully controlled-access freeway, it would not have met Interstate standards due to two key design features: First, opposing lanes of traffic would have been separated by a concrete Jersey barrier versus the wide median on the existing Route 11 section.

Secondly, the greenway was being planned to have curve radii that would have been tighter than what is allowed by Interstate standards, although it would have still had a design speed of 70 mph (110 km/h).

As of 2010, the Authority still held monthly meetings and the funds from the State of Connecticut still existed to purchase land for the Greenway, despite the near certainty the expressway itself would never be completed.

An interchange with Interstate 95 and 395 was also planned to be built as part of the highway extension, and accounted for about half of the $1 billion cost of the project.

Aerial view of the split between Route 11 (bottom left) and Route 2
CT 11 approaching its intersection with CT 2