DeLong pier

First used during the Vietnam War at Cam Ranh Bay, the DeLong pier was originally designed shortly after the Second World War by the DeLong Corporation, and a prototype was constructed not long after in Charleston, South Carolina for use by the Transportation Corps in 1952.

This prototype would, in late 1965, be the first of four DeLong piers installed in the bay by the 497th Port Engineer Company.

The crane then operates a pile driver on each caisson to drive it into the seafloor.

After this, the specially designed pneumatic jacks are lowered over the caissons, secured to the decks of the component barges, and begin to lift the barges above the water to create a pier of any desired height.

After fenders are installed and construction equipment removed, the whole process was said to take between two and four weeks, depending on purpose, with a team of twelve workers.

DeLong pier at Vũng Rô Bay , Vietnam, in 1968