Eliot station was made accessible in October 2024; additional reconstruction is planned to begin in 2026.
[1] In 2019, the MBTA indicated that the four remaining non-accessible stops on the D branch were "Tier I" accessibility priorities.
[5] A preliminary design contract for accessibility modifications at the four stations was issued in February 2021.
[8][9] Plans shown in March 2024 called for the platforms to be rebuilt in their existing configuration.
[12] Construction at the four stations took place primarily over the weekends of October 5–6 and 19–20, 2024, leaving them "generally accessible".