[4] Phase 1 of the SR 9B/I-795 project, consisting of a three-mile (4.8 km) spur from the Eastern Beltway of I-295 to US 1, began in the middle of 2010 and was scheduled to be completed in early of 2013, at an estimated cost of $68.5 million.
The winning contract went to Archer Western Contractors / GAI Consultants, who also reconstructed the I-10/I-95 interchange in downtown Jacksonville.
[5] The roadway was originally planned to open in the end of 2012, but was pushed back to 2013 to allow for the construction of a wider paved area to facilitate future expansion.
[6] In late July 2013, southbound I-295 was closed a few nights to install new overhead signs for the SR 9B interchange, one of the final construction projects of Phase 1.
Phase 3 consisted of extending State Road 9B 2.3 miles (3.7 km) south of the Interstate 95 interchange.