Golden Eagle Oilfield

[3] Approval for the Golden Eagle Area Development project was granted by the UK Department of Energy and Climate Change in October 2011 and production began in November 2014 at a rate of 18,000 barrels of oil a day.

[5] Heerema was commissioned to build the jackets for the two platforms, which were delivered in 2013, while Technip supplied and installed the subsea equipment.

CB&I was awarded the contract for engineering design of the topsides, which were built by Lamprell in Dubai and delivered in June 2013 (WHP) and April 2014 (PUQ).

[1][2] Sembmarine SLP was awarded the contract for engineering, procurement and construction of the 140-person, six-level accommodation module, with a lightweight aluminium flooring system supplied by Alphastrut, which was installed in May 2014.

[6][7][8] Sembmarine SLP also won the contract to build the bridge structure, while GE Oil & Gas provided production and control equipment.