Numerous problems with the class were exposed by the lengthy sea trials period undertaken by the boat; Collins was not commissioned into the RAN until mid-1996, eighteen months behind schedule, and the submarine was not cleared for operational deployments until 2000.
With the decommissioning of HMAS Anzac on 18 May 2024, Collins became the First Lady of the Fleet as the longest serving commissioned RAN vessel.
[citation needed] It was originally planned to construct the first submarine completely overseas, but by the time the tender was awarded, it had been decided to build all six submarines in Australia; the increase in cost by not building the lead ship in the winning designer's home shipyard were believed to be offset by the additional experience provided to Australian industries.
[13][14] The hull is constructed from high-tensile micro-alloy steel, and are covered in a skin of anechoic tiles to minimise detection by sonar.
[14][18][19] Each submarine is equipped with three Garden Island-Hedemora HV V18b/15Ub (VB210) 18-cylinder diesel engines, which are each connected to a 1,400 kW, 440-volt DC Jeumont-Schneider generator.
[23] During sea trials, the submarine was often forced back to port because of equipment problems, where the Navy personnel found that ASC engineers would diagnose and repair systems using a combination of supplier data and diagnostic tools not available to the sailors.
[26] Evaluation of the submarine was based on attaining a series of licenses, gradually testing the capabilities of Collins and those operating her from surface sailing to deep, unaccompanied dives.
[28] Although sea trials resumed in early 1995, Collins did not dive again until 9 June, when it was decided that the status of the combat system drop was sufficient to allow further underwater tests of the submarine.
[29] The tests went without difficulty until the next day, when the anchor cable snapped in poor weather, forcing Collins to return to port.
[29] When approaching the ASC wharf, a programming problem with the propulsion switchboard caused the main motor to cut out.
[31] On this occasion, the water pressure meant the flow rate was significantly greater, to the point where the aft bilge pump was barely keeping up.
[31] When the senior engineer entered the compartment, he found personnel trying to stem the flow, including one sailor who was underneath the shaft, attempting to tighten the seal manually.
[32] Recurring issues were usually associated with diesel engines, propeller shaft seals, periscopes and masts, hydraulic couplings, and the combat system.
[28] The submarine was not commissioned into the RAN until 27 July 1996; eighteen months behind schedule, because of several delays and problems, most relating to the provision and installation of the combat data system software.
[16] In May 1997, two groups of six female sailors were posted to Collins and Farncomb as a test on the feasibility of mixed-sex crews aboard submarines.
[43][44] In July 2009, while exercising in the Great Australian Bight, two of the three diesel generators aboard Collins failed, forcing the submarine to limp back to base.