[1] As all traffic going northbound to Inverness via the A96 or southbound to Dundee via the A92 must pass through this roundabout it is a notoriously busy and hazardous junction with large queues approaching all directions to the roundabout, especially during rush hour.
In addition improvements are planned to help ease the congestion at the roundabout.
[6] The project required 127 flats to be demolished, this occurred in 2018.
[7] In December 2019, Farrans Construction was appointed as contractor for the project.
[9] The project was originally expected to be completed by spring 2021; however, this was pushed back to winter 2021.