[3] Indianapolis Power & Light (IPL) has a 20-year contract to purchase and distribute the wind farm's output.
[4] IPL and enXco announced their plan to build the wind farm in April, 2008.
[4] The original plan called for 67 GE 1.5 MW wind turbines.
[4] By the time construction started in April 2009, the plan had changed to use REpower 2.0 MW wind turbines instead, with 80m towers.
[5] IPL expects Hoosier to generate enough power for 29,000 homes and reduce carbon dioxide emissions by 348,000 tons per year.