It was the first large hydroelectric power station constructed in Eastern Siberia and its completion was hailed by the Soviets as an engineering success.
In 1935, the research stage of the study was complete and recommended a hydroelectric power plant at the top of the Angara for industrial consumption.
In 1936, the State Plan of the USSR reviewed the results and determined that six hydroelectric power stations in a cascade should be built on the river, the Irkutsk being the first.
[4] Construction on the Irkutsk HPS began in February 1950 and was conducted by Angaragesstroy with Anton Melnikonis managing.
On July 7, 1956, the river was cut off to allow the filling of the Irkutsk Dam's reservoir and on December 29 of that same year, its first generator began to produce electricity.
In 1960, by decree of the Presidium of the Supreme Council of the USSR, 349 workers, engineers and employees including Bochkin were awarded Hero of Socialist Labour medals for the outstanding success of the HPS.