Jamshoro Power Station

[2] [3] The power station is undergoing a planned expansion with additional 2 x 660 MW coal fired units.

Site preparation of second 660 MW unit is in progress with an expected commissioning date of July 2029.

[4] In February 2014, the Asian Development Bank agreed to loan $900m to the government of Pakistan for a project to install 2 x 660MW supercritical coal-fired power plant at Jamshoro.

[5] The Islamic Development Bank (IDB) approved $220m for the Jamshoro Coal Power generation project.

Unit 5 of 660 MW will be using an 80/20 blend of imported sub-bituminous coal (80%) and domestic lignite (20%) from Thar coalfield.