Jose Rizal-class frigate

[7] The ships, which were built by Hyundai Heavy Industries (HHI), are specifically accommodated to fit the requirements of the Philippine Navy.

[11][12][13] For the 1st stage bidding, only four shipbuilders were declared as qualified, with GRSE, STX France, and TKMS disqualified for failing to meet documentation requirements.

[14] With six proponents passing the first stage bidding phase, successive meetings were held with the Philippine Navy, wherein the DND found out restrictions in the export of munitions through third party shipbuilders.

The ABC was also increased to Php 16 billion (around US$355 million) to cover for the peso's declining value over the US dollar, and to allow the improvements of the ships' key features.

The joint DND-PN team conducted the post-bid qualification inspection of GRSE in June 2016, wherein they found that it did not meet financial requirements, specifically the Net Financial Contracting Capacity (NFCC), which gave the DND-PN team a reason to conduct a post-bid qualification inspection with the second lowest bidder, HHI.

This was done and completed in July 2016, wherein the team found that HHI was able to comply with the requirements and was considered the Lowest Post-Qualified Bidder while declaring GRSE as Post-Disqualified.

Delfin Lorenzana, and Hyundai Heavy Industries, represented by its Senior Vice President Mr. Ki Sun Chung, under the presence of officials from the DND, AFP, PN, HHI, and the South Korean Ambassador to the Philippines.

Lincuna said TIAC's acceptance of the CDR marks a significant step forward and a milestone for the project, which consists of the approval of 71 critical detailed design drawings as submitted by HHI.

[45] On September 17, 2018, the steel cutting ceremony was held for P160 (project number of second of two frigates) at HHI shipyard at the Shin Hwa Tech facility in Pohang City, South Korea, marking the first step of the ship's construction journey.

[46] On November 8, 2019, HHI launched the second ship, the prospective BRP Antonio Luna, at Ulsan shipyard in South Korea.

[51] On February 9, 2021, the ship was met by BRP Jose Rizal and three FA-50 jets in the vicinity of Capones Island, Zambales having departed South Korea four days prior.

[53] Issues arose over the decision made by HHI without approval by the Philippine Navy to use the Alternative Configuration in the selection of systems to be installed.

Go's office also asked then Frigate Project Technical Working Group chairman Commodore Robert Empedrad, to attend a meeting in Malacañang to discuss the selection of the CMS.

DND public affairs office chief Arsenio Andolong made the statement in response to plans of the Senate minority bloc to conduct an investigation on the Frigate Acquisition Project (FAP).

A case stemmed in 2013, after its top executive was found guilty of offering bribes in order to win the bid to supply parts for four nuclear reactors to be constructed at the United Arab Emirates.

[60] Mercado was unceremoniously replaced by Rear Adm. Robert Empedrad over the controversial P18-billion frigate acquisition project with South Korea's shipbuilder Hyundai Heavy Industries.

A scale model of HDF-2600 Frigate during ADAS 2018