Omega Morgan

[4] At the time the company had grown to 275 employees and had revenues of $42 million in 2010[4] and had an office in Fife, Washington, along with the headquarters in Hillsboro.

[16] The company also acquired full control of its shares in its three-year crane services joint venture with Sarens LLC.

In 2023 Omega Morgan acquired Intermountain Rigging and Heavy Haul, a Salt-Lake city based heavy haulage company which in a result increased its geographical presence and fleet size.Omega Morgan hauled the Canby Ferry to Portland in April 2012 due to the closure of the Willamette Falls Locks.

[19] In January 2013, working with Multnomah County government, Omega Morgan moved the 6.8-million pound main 1,100-foot (340 m) section of the Sellwood Bridge in Portland, Oregon from its current location onto new pylons.

[25] In September 2013, they moved the replacement span into place as part of the repairs to the Skagit River bridge in Washington.

The project required the acquisition of 39 permits and authorizations to account for heavy traffic conditions in the area, noise restrictions, and road closures.

Due to the complicated nature of the project, Omega Morgan’s crews performed several rounds of modeling and testing before moving forward to execute the plan.

Omega Morgan headquarters - Hillsboro, Oregon
Move of the Sellwood Bridge