Operation Pacer HO

Modification of the redrumming facility, installation of needed utilities and communications, and requisitioning/positioning of logistics support (i.e., R-5 refuelers, forklifts, personnel protective equipment) were accomplished in May and June in preparation for the re-drumming operation.

[2] From May to June 1977, Air Force personnel from the five Combat Logistics Support Squadrons (CLSS) on Temporary Duty at the U.S.

The Vulcanus, with its crew of 18 foreign nationals and the load of HO from Gulfport, Mississippi, arrived at Johnston Atoll on July 10, 1977.

The monitoring equipment that had been airlifted to Johnston Atoll from the TRW Corporation at Redondo Beach, California, was immediately installed.

It flew from Hickam AFB to Johnston Atoll with a special seat configuration for 80 passengers and brought 61 new employees to perform the de-drumming.

[2] In the interim and following two days of debriefings, EPA representatives granted permission on July 27, 1977, to proceed with the de-drumming of the HO stored at Johnston Atoll.

To ensure no harm occurred to the crew or monitors, complete physicals were given to 26 people at the Johnston Atoll dispensary while the ship was being loaded for the second burn.

[2] Based on the analysis of the exhaust samples from the first burn, a permit was issued on August 4, 1977, authorizing incineration of the remaining HO at Johnston Atoll.