In 2006, the first turbogenerator plant was reconstructed (new equipment was installed—a 6 MW steam turbine of the type GTPA-631 produced by OAO Kirovsky Zavod and a turbogenerator of the T-6-2U type produced by JSC Privod in Lysva).
In early 2009, the TG-2 (MK-2,5) was decommissioned due to complete physical deterioration and the inability to continue operation.
Generation of electricity is carried out with the help of turbines operating on the geothermal steam of the Pauzhetskoye (Kambal) hydrothermal field.
The available capacity of the power plant is 6.0 MW and is limited by the amount of geothermal steam supplied.
On 1 January 2006, the power plant was separated from OJSC Kamchatskenergo and began operating as an independent legal entity—OJSC Pauzhetskaya GeoPP.