Ruzibazi Hydroelectric Power Station

The Ruzibazi Hydroelectric Power Station is in Rutumo colline, Minago zone in the Commune of Rumonge.

[2] The agreement between China and the Burundian Ministry of Energy and Mines was signed on 26 August 2016.

[3] Construction by the Chinese company Sinohydro began in October 2018 and was completed ahead of schedule in July 2022.

It was inaugurated on 6 September 2022 in a ceremony attended by Evariste Ndayishimiye, President of Burundi.

The Kabezi section of the dispatching center in Ngagara in the commune of Ntahangwa and the substation were not yet complete, but were expected to be ready on time.