Thune Dam

[4] Once complete, water will be delivered to the villages of Bobonong, Motlhabaneng, Mathathane, Tsetsebjwe, Mabolwe, Semolale, Gobojango, Lepokole and Molalatau.

[3] A stakeholders workshop was held in September 2009 at Molalatau Secondary School Hall, where the Minister provided information and answered questions.

[3] The dam site was handed over to the contractor, Zhon Gan Engineering and Construction, on 30 April 2010.

In July 2010 it was reported that work on the dam site had halted since an incident in which a worker was killed a month earlier.

[4] A ground-breaking ceremony was held in September 2010, attended by Ponatshego Kedikilwe, Minister of Minerals, Energy and Water Resources.