The Second Avenue Line was originally proposed in 1919 as part of a massive expansion of what would become the Independent Subway System (IND).
[4] Numerous plans for the Second Avenue Subway appeared throughout the 20th century, but these were usually deferred due to lack of funds.
[8] The Metropolitan Transportation Authority proposed a full-length Second Avenue Subway as part of its 1968 Program for Action.
[12] All Second Avenue Subway stations built under the Program for Action would have included escalators, high intensity lighting, improved audio systems, platform edge strips, and non-slip floors to accommodate the needs of the elderly and people with disabilities, but no elevators.
[13] The stations were to be made with brick walls and pavers alongside stainless steel, and would have relatively small dimensions, with 10-foot (3.0 m) mezzanine ceilings.
[14]: 110 A combination of Federal and State funding was obtained, and despite the controversy over the number of stops and route, a groundbreaking ceremony was held on October 27, 1972, at Second Avenue and 103rd Street.
[11][15][16] Construction began shortly thereafter on what was to be the 99th–105th Streets segment, which was projected to cost $17.48 million (worth about $127,324,000 today).
In their request for funding, they cited that they wanted to avoid an uncertain response from the first administration of Donald Trump and start construction on Phase 2 as soon as possible.
[37] In January 2017, it was announced that Phases 2 and 3, which are expected to cost up to a combined $14.2 billion, were on the Trump administration's priority list of 50 most important transportation projects nationwide.
[40]: Figure 2-1A Under the new plan, the station would also include extra elevators in compliance with the Americans with Disabilities Act of 1990.