Nanyang Gateway MRT station is a future elevated Mass Rapid Transit (MRT) station on the Jurong Region line in Western Water Catchment, Singapore.
The station will be located within the Nanyang Technological University (NTU).
On 9 May 2018, the Land Transport Authority (LTA) announced that Nanyang Gateway station would be part of the proposed JRL.
[3] However, the restrictions on construction due to the COVID-19 pandemic has led to delays, with the completion date pushed to 2029.
[4] The contract for the design and construction of the Nanyang Gateway and Nanyang Crescent stations and 1.4 km (0.87 miles) of associated viaducts – Contract J113[5] – was awarded to Hwa Seng Builder Pte Ltd at S$263 million (US$192.8 million) on 6 April 2021.