Jurong Pier MRT station is a future elevated Mass Rapid Transit (MRT) station on the Jurong Region Line (JRL), located on the boundary of Boon Lay and Jurong East planning areas in Singapore.
Trains entering service at this station will terminate at Peng Kang Hill via Bahar Junction.
On 9 May 2018, the Land Transport Authority (LTA) announced that Jurong Pier station would be part of the proposed JRL.
[2] However, the restrictions on construction due to the COVID-19 pandemic has led to delays, with the completion date pushed to 2029.
[3] The contract for the design and construction of the Jurong Hill and Jurong Pier stations and 1.1 km (0.68 miles) of associated viaducts – Contract J112[4] – was awarded to a joint venture between China Civil Engineering Construction Corporation (Singapore Branch) (CCECC) and SCB Building Construction Pte Ltd at S$263 million (US$192.79 million) on 6 April 2021.