Its construction began in February 1885, being intended to provide a connection between Berber on the River Nile and Suakin on the Red Sea littoral for the rapid deployment of troops and military equipment in Britain’s involvement in the Mahdist war.
In May 1885, after barely three of months of work during which only 20 of the intended 280 miles of track had been laid, at a cost approaching £1 million, Britain suspended its war with the Mahdi, pulled out of the Sudan and terminated the Suakin-Berber railway.
[1] In 1883 Britain became involved in hostilities against the Mahdi revolt, sending General Gordon to Khartoum to organize the evacuation of military and civilian staff and families.
The contract required Lucas and Aird to work under the direction of General Sir Gerald Graham, commander of the Suakin Field Force that had been sent out to protect the railway against rebel attack.
Construction work was impeded by the poor quality labour force and by the (second hand) materials and rolling stock sent out from Britain - a situation that was exacerbated by attacks and sabotage by the enemy.
[4] In April 1885, the Panjdeh incident in which Russian forces seized Afghan territory and thereby threatened India, gave the Gladstone government justification to pursue its anti-imperialist policies by terminating British involvement in the Sudan.