Van Buren Street Bridge

[2] Benton County legislators were able to secure approval to build a bridge at the site as early as 1889.

[6] Work began about June 1912 after a legal delay over funding was resolved, with Corvallis agreeing to pay a larger portion of the project.

[7] In November 1912, Corvallis residents passed a bond measure to allow for the city's portion of funding of the bridge.

[9] The span was completed in February 1913,[2] with a dedication ceremony on March 11 attended by the mayors of Corvallis and Philomath, as well as the judges for Linn and Benton counties.

[15] In the 1990s the Oregon Department of Transportation proposed options for replacing the bridge in order to alleviate traffic problems in downtown Corvallis.

[17] Linn County's Board of Commissioners supported tearing down the old bridge and simply replace it with a new wider span.

[19] Additional studies began in 2007 to determine which of the options for replacement would work best for fixing traffic issues across the river.

[20] As of 2015 the plans for a new bridge had been set aside, with improvements to the south bypass and downtown exits for OR 34, OR 20, and 99 W intended to ease congestion instead.

The future northern bypass is considered by planners to be a long-term goal, as there is no schedule and none of the estimated $250 million cost has been budgeted.

[12] A swing bridge, its main 249-foot (76 m)-span could swivel on its axis and open to allow river traffic to pass.

[9] This would turn the 24-foot (7.3 m) wide gear that had 300 teeth along its circumference and the span would spin along 42 rollers constructed of steel.

[12] Overall, the bridge was 708 feet (216 m) long and was composed of three separate steel spans that rested on concrete piers.

Entrance to the bridge from the west
Western side of the bridge