The station is approximately 292 kilometres (181 mi), by road, north-northwest of Kampala, the capital and largest city of Uganda.
In December 2010, bids for an environmental impact study, power station design, and cost estimation were solicited in the Ugandan media.
The developer was going to be the Uganda Electricity Generation Company Limited (UEGCL), a government parastatal, in partnership with a private investor.
In February 2014, UEGCL applied to Uganda's Electricity Regulatory Authority for a license to generate up to 44.7 megawatts of power at Muzizi.
The funds include the cost of building the high-voltage transmission lines that will evacuate the power to the point where it will be integrated into the national electricity grid.
[14] In August 2015, UEGCL, the implementing Uganda government agency, selected the consulting engineers, who will review feasibility studies that have been done by other companies, design the project, and prepare tender documents for a fee of €3,959,771 (about UGX:15.5 billion).